M5J10 Information Session – 07/03/24
Information letter from Glos Highways Page 1
Information Letter from Glos Highways Page 2
M5 Junction 10 Improvements Scheme: PLANNING ACT 2008 SECTION 56: NOTIFYING PERSONS OF ACCEPTED APPLICATION
THE INFRASTRUCTURE PLANNING (APPLICATIONS: PRESCRIBED FORMS AND
PROCEDURE) REGULATIONS 2009: REGULATION 8
THE INFRASTRUCTURE PLANNING (ENVIRONMENTAL IMPACT ASSESSMENT)
REGULATIONS 2017: REGULATION 16
We are writing to you with regards to our M5 Junction 10 Improvements Scheme (the ‘Scheme’). The Scheme’s aim is to remove current constraints on the highway network, improve connectivity between the Strategic Road Network and the local transport network, and ensure there is enough capacity to accommodate traffic demand associated with planned housing and employment growth in the area. The Scheme also aims to provide safe access to services for the local community and for active travel users, as well as establishing biodiversity net gain and meeting climate change requirements.
The Scheme will deliver:
- Improvements to M5 Junction 10.
- A new road linking Junction 10 to West Cheltenham.
- Widening of the A4019 Tewkesbury Road.
Further information about the Scheme is available at: https://www.gloucestershire.gov.uk/highways/major-projects-list/m5-junction-10-improvements-scheme/
Gloucestershire County Council (GCC) is seeking a Development Consent Order (DCO) for the Scheme under the Planning Act 2008 (the ‘2008 Act’). This legislation requires GCC to make an application to the Planning Inspectorate (‘the Inspectorate’) for a DCO to obtain the consent we need to build the Scheme.
The Inspectorate received GCC’s application for a DCO on 19 December 2023. This application was accepted for examination by the Inspectorate (on behalf of the Secretary of State) on 16 January 2024. We are writing to you because it is a requirement for us to notify you of an accepted application.
In accordance with the Planning Act 2008 and the Infrastructure Planning (Environmental Impact Assessment) Regulations 2017, please find links in the table below that will direct you to the following information:
Document | Link |
A copy of a Section 56 notice, providing formal notification of acceptance of the application | A copy of the Section 56 notice accompanies this email. |
A copy of the accepted application | https://FiletransferGB.atkinsglobal.com/message/2kb5FQFAY8Hj770bFxHV1c |
Detailed maps showing the location and site of the proposed scheme | |
A copy of the Environmental Statement |
Please note that the file transfer link will expire on 22 February 2024 but a full schedule of application documents can also be viewed by accessing:
https://national-infrastructure-consenting.planninginspectorate.gov.uk/projects/TR010063/documents
Further information regarding the availability of the DCO application documents and where you can view them is included in the enclosed Section 56 notice.
Any person may make representations on the application to the Secretary of State (that is: giving notice of any interest in or objection to the application). Details of the way in which representations must be made are included in the enclosed Section 56 notice.
Representations must be received by the Inspectorate no later than 11:59pm on 22 March 2024. Please note that any representations submitted to the Inspectorate will be published on the National Infrastructure Planning website for the application.
For further information about the application, please contact us using the following details:
- Email: M5Junction10@atkinsrealis.com
- Telephone: 01454 667900
- Post: ‘FREEPOST M5 JUNCTION 10’
Kathryn Haworth
Senior Responsible Officer; Major Projects
Gloucestershire County Council
S56 Notice FINAL
M5 Junction 10 Improvements Scheme – Additional Targeted Non-Statutory Consultation.
Additional targeted consultation on further proposed changes to our scheme design.
The additional targeted consultation period will be 29 days, from 00:01hrs on Monday 8
August 2022 until 23:59hrs on Monday 5 September 2022. This targeted consultation will
be for relevant prescribed consultees and Persons With an Interest in Land.
GCCM5J10-ATK-GEN-ZZ-DR-CH-000005_C01
GCCM5J10-ATK-GEN-ZZ-DR-CH-000006_C01
GCCM5J10-ATK-GEN-ZZ-DR-CH-000007_C01
GCCM5J10-ATK-GEN-ZZ-DR-CH-000008_C01
GCCM5J10-ATK-GEN-ZZ-DR-CH-000009_C01
GCCM5J10-ATK-GEN-ZZ-DR-CH-000010_
C01 GCCM5J10-ATK-GEN-ZZ-DR-CH-000011_C01
GCCM5J10-ATK-GEN-ZZ-DR-CH-000012_C01
GCCM5J10-ATK-GEN-ZZ-DR-CH-000013_C01
GCCM5J10-ATK-GEN-ZZ-DR-CH-000014_C01
GCCM5J10-ATK-GEN-ZZ-DR-CH-000015_C01
Minutes of the Research Meeting With Elmstone Hardwicke/Uckington Parish Councils,
Gloucestershire County Council & Atkins – 7th July, 2022
EH&UPCsMtng-07-07-22 Report
Feedback Survey
Indicative Application Red Line Boundary Plan
M5 Junction 10 Section 47 Notice
M5 Junction 10 Section 48 Notice
PEIR Chapters 1 – 4 Introduction and Assessment Approach
PEIR Chapter 5 Air Quality
PEIR Chapter 6 Noise and Vibration
PEIR Chapter 8 Road Drainage and the Water Environment
PEIR Chapter 9 Landscape and Visual
PEIR Chapter 10 Geology and Soils
PEIR Chapter 11 Cultural Heritage
PEIR Chapter 12 Materials and Waste
PEIR Chapter 13 Population and Human Health
PEIR Chapter 14 Climate
PEIR Chapter 15 Cumulative Effects Assessment
PEIR Non-Technical Summary (NTS)
Scheme Plan